The Ploiești Autonomous Public Services Authority (Regia Autonomă de Servicii Publice) monitors, on a weekly basis, a series of repair and investment works scheduled with a view to improving the public services of the municipality of Ploiești, as follows:
- PT 11 Republicii, Gh. Doja Street intersection with Văleni Street, behind block 45F3 – Repair of secondary heating network failure;
- PT 11 Centru, Pecef connection, Artem, Mihail Kogălniceanu Street, behind Block C3 – Repair of secondary heating network failure ACI;
- PT 16 Democrației, ANAF connection, Federal Coop, behind ANAF building, building located on Democrației Street, no. 62 and Cumpătul Street no. 6 – Repair of secondary heating network failure ACI.
Replacement investment works carried out by Apa Nova Ploiești:
- Sewer network and connections – Rucăr Lane.
During the same period, the operator Apa Nova Ploiești will also carry out a series of works for the extension and modernisation of the local water and sewer infrastructure, in accordance with the Compliance Investment Plan – Annex 3 to Addendum no. 4 to the Concession Contract approved by HCL no. 183/29.04.2025, as follows:
- Wastewater treatment micro-station – Mitică Apostol neighbourhood;
- Water network and connections, Cerbului Street;
- Water network and connections, Prigoriei Street;
- Water network and connections, Violetelor Street;
- Water network and connections, Canarului Street;
- Water network and connections, Lăstunului Street;
- Water network and connections, Paltinului Street;
- Water network and connections, Trestioarei Street;
- Water network and connections, Fluturilor Street;
- Water network and connections, Mierlei Street;
- Water network and connections, Energiei Street;
- Water network and connections, Acvilei Street;
- Water network and connections, Brândușelor Street;
- Water network and connections, Ferigii Street;
- Water network and connections, Răchitei Street;
- Water network and connections, Ciocârliei Street;
- Water network and connections, Gaterului Street;
- Water network and connections, Delfinului Street;
- Water network and connections, Plutelor Street;
- Water network and connections, Viilor Street;
- Water network and connections, Cetinei Street;
- Water connections execution, Brădetului Street;
- Water connections execution, Smârdan Street;
- Sewer connections execution – Bobâlna Street;
- Sewer connections execution – Traian Vuia Street;
- Sewer connections execution – Brâncoveanu Vodă Street;
- Sewer network extension – Borzești Lane intersection with Tudor Vladimirescu Street.
We thank the residents of these areas for their understanding!