The Ploiești Autonomous Public Services Authority monitors, weekly, a series of repair and investment works, scheduled with a view to improving the public services of the Ploiești municipality, as follows:

PT 2 Nord, pedestrian passage Complex Nord between Șoseaua Nordului and Aleea Brebenei – secondary thermal network ACI failure repair;

  • PT 12 23 August, Elena Doamna Street, in front of block 32I – secondary thermal network ACC failure repair;
  • PT 2 23 August, Gh. Grigore Cantacuzino Street, side of Block 3D2-Casa Capra – secondary thermal network ACC failure repair;
  • MT branch block 30B, Libertății Street, behind block 30B – primary network failure repair.

Ongoing works in the Apa Nova Ploiești programme this week are as follows:

Investment works – replacements:

  • Sewerage network and connections Baciului, Stanelor, Mocanilor streets;
  • Sewerage network and connections Libertății Street, blocks 85, 86, 87, 88, 89, 91;
  • Water network and connections Luminii Street and behind blocks 30D, 30E, 30F, 30G;
  • Sewerage network and connections Curcubeului Street;

Works that are part of the Compliance Investment Plan – Annex 3 to Addendum no. 4 of the Concession Contract approved by HCL (Local Council Decision) no. 183/29.04.2025:

  • Treatment microstation – Mitică Apostol neighbourhood;
  • Water network and connections Cerbului Street;
  • Water network and connections Prigoriei Street;
  • Water network and connections Violetelor Street;
  • Water network and connections Canarului Street;
  • Water network and connections Lăstunului Street;
  • Water network and connections Paltinului Street;
  • Water network and connections Trestioarei Street;
  • Water network and connections Fluturilor Street;
  • Water network and connections Mierlei Street;
  • Water network and connections Energiei Street;
  • Water network and connections Acvilei Street;
  • Water network and connections Brândușelor Street;
  • Water network and connections Ferigii Street;
  • Water network and connections Răchitei Street;
  • Water network and connections Ciocârliei Street;
  • Water network and connections Gaterului Street;
  • Water network and connections Delfinului Street;
  • Water network and connections Plutelor Street;
  • Sewerage network and connections Rafinorilor Street;
  • Sewerage network and connections Foișor Street;
  • Sewerage network and connections Alexandru Machedon Street;
  • Sewerage network and connections Tatra Street.

We apologise for any inconvenience caused during the works and thank residents for their understanding and support!

We are constantly modernising the local infrastructure and providing quality public services for Ploiești residents!

DIRECȚIA COMUNICARE, RELAȚII PUBLICE ȘI SITUAȚII DE URGENȚĂ (Communication, Public Relations and Emergencies Department)