Regia Autonomă de Servicii Publice (Autonomous Public Services Authority – R.A.S.P.) Ploiești monitors, on a weekly basis, a series of repair and investment works scheduled to improve the public services of the municipality of Ploiești.
Below, we present the updated status of the main works under way:
- PT 1 Vest, Erou Moldoveanu Marian Street, in front of Block 9A, entrance A – Repair of secondary heating network failure RACC;
- PT 11 Centru, Pecef Connection, Artem, Mihail Kogălniceanu Street, behind Block C3 – Repair of secondary heating network failure ACI;
- PT 6-9Mai, Cireșoaia Street, side rear of Blocks 18G-18H3;
- PT 11 Republicii, Gh. Doja Street intersection with Văleni Street, behind Block 45F3.
During the period mentioned, the operator Apa Nova Ploiești will also carry out a series of works to extend and modernise the local water and sewerage infrastructure, in accordance with the Compliance Investment Plan – Annex 3 to Addendum no. 4 to the Concession Contract approved by HCL (Local Council Decision) no. 183/29.04.2025, as follows:
- Wastewater treatment microstation – Mitică Apostol neighbourhood;
- Water network and connections, Cerbului Street;
- Water network and connections, Prigoriei Street;
- Water network and connections, Violetelor Street;
- Water network and connections, Canarului Street;
- Water network and connections, Lăstunului Street;
- Water network and connections, Paltinului Street;
- Water network and connections, Trestioarei Street;
- Water network and connections, Fluturilor Street;
- Water network and connections, Mierlei Street;
- Water network and connections, Energiei Street;
- Water network and connections, Acvilei Street;
- Water network and connections, Brândușelor Street;
- Water network and connections, Ferigii Street;
- Water network and connections, Răchitei Street;
- Water network and connections, Ciocârliei Street;
- Water network and connections, Gaterului Street;
- Water network and connections, Delfinului Street;
- Water network and connections, Plutelor Street;
- Water network and connections, Viilor Street;
- Water network and connections, Cetinei Street;
- Water network and connections, Buftea Road – DN1A;
- Water connections installation, Brădetului Street;
- Water connections installation, Smârdan Street;
- Sewerage connections execution – Bobâlna Street;
- Sewerage connections execution – Enăchiță Văcărescu Street;
- Sewerage connections execution – Traian Vuia Street;
- Sewerage connections execution – Brâncoveanu Vodă Street.